WSDOT and crews are in the third construction season on the I-90 Snoqualmie Pass — Hyak to Keechelus Dam project. In this time lapse video, you can watch construction of the Gold Creek Bridges from 2010 — 2011.
In 2010, crews installed 120-foot deep bridge foundations, and part of the animal under crossing at Gold Creek Bridge. In 2011, crews set girders, poured bridge decks, and will finish the eastbound animal under crossing and bridge at Gold Creek by fall 2011.
For more information on the funded five mile project: Hyak to Keechelus Dam Project – wsdot on YouTube